Harenberg 117–161

Bruxelles · 04/IPEEXT/474397 · Extension / Transformation de PE

Harenberg 117–161, Bruxelles: operation of installations. Case octroyé, lodged on 29 August 2012. The decision was notified on 18 September 2012, 20 days after lodging.

Ajout d'une cabine haute tension
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on29 August 2012date the file was received
Decision notified18 September 201220 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
28 mExtension or raisingd’une part, construire une annexe, modifier la façade avant (mise en conformité), et d’autre part, construire une annexe2024
28 mExtension or raisingd’une part, abattre les arbres du jardin et en replanter 7, démolir un WC dans la zone de cour et jardin, modifier la po2025
43 mFaçade and windowsRemplacer les châssis en bois brun par des châssis en PVC de ton gris anthracite (mise en conformité)2023
90 mExtension or raisingd'une part, changer les châssis en façade par des châssis en PVC blancs et placer une fenêtre de toiture à l'avant d'une2022
92 mExtension or raisingd'une part, changer les châssis en façade d'une maison unifamiliale par des châssis en PVC blanc, construire une extensi2024

Other nearby cases : 04/PU/1940919, 04/PU/1847020, 04/PU/1846971, 04/PU/1950018, 04/PU/1907673, 04/PFD/2019804, 04/PU/2019240, 04/PU/1843993, 04/SFD/1864995, 04/PU/1810861, 04/PU/1862076, 04/PU/1936058, 04/PU/1955673, 04/PU/1908294, 04/PU/1837239, 04/PU/1828968

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)