Rue du Marais 30

Bruxelles · 04/IPEEXT/486570 · Extension / Transformation de PE

Rue du Marais 30, Bruxelles: operation of installations. Case annulé, lodged on 26 April 2013. The decision was notified on 22 May 2013, 26 days after lodging.

As-built dossier na aanpassingen splitsing site.
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on26 April 2013date the file was received
Decision notified22 May 201326 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
8 mOffice conversionObjet de la demande amendée : Démolir le bâtiment E (Rothschild) en intérieur d’ilot et transformer un ensemble de deux2023
51 mFaçade and windowsRemettre en peinture et restaurer (légèrement) les façades classées du bâtiment du Grand Temple2023
69 mStudent housingRénovation, extension et transformation d'un immeuble de bureaux en logements pour étudiants.2023
69 mOtherDans le cadre des travaux, le propriétaire souhaite procéder à un habillage esthétique de l’échafaudage pendant la durée2026
74 mHeavy renovationRénover complètement et réaménager le bâtiment du cabinet2025

Other nearby cases : 04/PFD/1911379, 04/PU/1962333, 04/PU/1998771, 04/PFD/1964589, 04/PFD/1937921, 04/PU/1968326, 04/PU/2007135, 04/PU/1998395, 04/PU/1833867, 04/PFD/2016654, 04/PFD/1840816, 04/PFD/2014045, 04/PFD/2009152, 04/PFU/1834394, 04/PFU/1848730, 04/PFU/1866504, 04/PFU/1989316, 04/PFD/1901601, 04/PU/1993866, 04/PFU/1867798, 04/PU/1955677, 04/PFU/1937029, 04/SFD/1840219, 04/SFD/1900367, 04/PU/1857736