Skip to content
Altaica Urban
Granted

Rue du Marais 57

Bruxelles · 04/IPEPLP/1867333 · Prolongation de PE

Rue du Marais 57, Bruxelles: operation of installations. Case octroyé, lodged on 16 December 2022. The decision was notified on 15 September 2023, 273 days after lodging.

Exploitation d'un théâtre
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on16 December 2022date the file was received
Decision notified15 September 2023273 days
Works started18 December 2023
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
32 mChange of useChanger l’affectation d’un l’immeuble de bureau en équipement sans modification de volume.2025
48 mPublic spaceplacer une rampe pour personnes à mobilité réduite sur le domaine public2022
66 mFaçade and windowsRestaurer les vitraux de l'atrium du centre Belge de la Bande Dessinée2025
67 mFaçade and windowsInstallation d’un caisson de volet (gris) au rez-de-chaussée2025
109 mChange of useModifier l’affectation de deux surfaces commerciales (l'une au rez-de-chaussée Meiboom, l'autre au dernier étage) vers2023

Other nearby cases : 04/PU/1821734, 04/PFD/2031436, 04/PFU/1967100, 04/PFU/1912838, 04/PFD/1906145, 04/PU/2042937, 04/PFD/2016510, 04/PFD/1916167, 04/PFD/2013392, 04/PU/1993866, 04/PFD/1926089, 04/PFD/1900090, 04/PFD/1915265, 04/PFD/1994556, 04/PFD/1911379, 04/PU/1830817, 04/PU/1990081, 04/PFD/1835128, 04/PFU/1997922, 04/PU/1868920, 04/PU/1819945, 04/SFD/1842614, 04/PU/1968326, 04/PU/1957309, 04/PU/1998771

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)