Granted

Boulevard Pachéco 36

Bruxelles · 04/IPEPLP/527393 · Prolongation de PE

Boulevard Pachéco 36, Bruxelles: operation of installations. Case octroyé, lodged on 16 May 2014. The decision was notified on 19 January 2015, 248 days after lodging.

Exploitation d'une gare
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on16 May 2014date the file was received
Decision notified19 January 2015248 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mChange of useModifier la destination d'une partie du bâtiment de bureaux vers équipement d'intérêt collectif ou de service public pou2022
0 mChange of useTransformer, rénover et rehausser la plinthe du bâtiment comprenant les espaces commerciaux, l'auditoire, le Passage 44 2021
82 mFaçade and windowsRénover les façades du bâtiment accueillant une partie de l'Institut Saint-Louis.2022
97 mHeavy renovationRéaménager l’entrée de l’université UCLouvain site BOTA 43 pour la rendre accessible PMR2025
97 mHeavy renovationRéaménager l’entrée de l’université UCLouvain site BOTA 43 pour la rendre accessible PMR2025

Other nearby cases : 04/PU/1970936, 04/PFD/2016510, 04/PFD/2013392, 04/PFD/1916167, 04/PFD/1900090, 04/PFU/1912838, 04/PFU/1967100, 14/PFU/1967918, 04/PU/1830817, 04/PU/1820659, 04/PU/2026708, 04/PU/2033571, 14/PFU/2020546, 14/PFU/1973798, 14/PFU/1928314, 04/PU/1938605, 04/PU/2037743, 04/PU/2042996, 04/PFD/2014045, 04/PU/1993866, 04/PU/1833867

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)