Rue du Meiboom 26
Bruxelles · 04/IPETMP/594308 · Permis d'environnement temporaire
Rue du Meiboom 26, Bruxelles: operation of installations. Case annulé, lodged on 1 March 2016. The decision was notified on 1 April 2016, 31 days after lodging.
Chantier Amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 1 March 2016 | date the file was received |
| Decision notified | 1 April 2016 | 31 days |
| Works started | 22 April 2016 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 73 m | Change of use | Changer l’affectation d’un l’immeuble de bureau en équipement sans modification de volume. | 2025 |
| 75 m | Façade and windows | Restaurer les vitraux de l'atrium du centre Belge de la Bande Dessinée | 2025 |
| 81 m | Signs and advertising | placer 1 mobilier urbain d’information avec support de publicité (BXL0417) | 2021 |
| 81 m | Tree felling | Abattre pour raison de sécurité un arbre à la gare du congrès | 2023 |
| 81 m | Façade and windows | Restaurer complètement le revêtement de sol de la salle des guichets et du remplacement du nom de gare sur le fronton de | 2024 |
Other nearby cases : 04/PFD/1903841, 04/PFD/2031436, 04/PU/1833867, 04/PU/1998395, 04/PU/1830817, 04/PFD/2016510, 04/PFD/2013392, 04/PFD/1916167, 04/PFD/1906145, 04/PU/2042937, 04/PU/1957309, 04/PFD/1994556, 04/PFD/1915265, 04/PFD/1826573, 04/PFD/1846498, 04/PFD/1900090, 04/PU/1993866, 04/PFD/1835128, 04/PU/2026708, 04/PFD/2037979, 04/PFD/1926089, 04/PFD/1846092, 04/PFD/1911379, 04/PFD/2016654, 04/PU/1968326
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)