Granted
Rue de l'Epée
Bruxelles · 04/PFD/146027 · Permis d'urbanisme délivré par le FD
Rue de l'Epée, Bruxelles: new construction. Case octroyé, lodged on 13 November 2002. The decision was notified on 12 August 2003, 272 days after lodging.
construire une brasserie.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 November 2002 | date the file was received |
| Consultation committee | 17 December 2002 | |
| Decision notified | 12 August 2003 | 272 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)