AltUrb
Granted

Donderberg

Bruxelles · 04/PFD/409066 · Permis d'urbanisme délivré par le FD

Donderberg, Bruxelles: new construction. Case octroyé, lodged on 21 December 2011. The decision was notified on 14 May 2012, 145 days after lodging.

bouwen van een lagere school met 6 klassen, een secretariaat en bijhorende sanitaire voorzieningen.
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on21 December 2011date the file was received
Public inquiry13 April 2012 – 28 April 2012
Consultation committee8 May 2012
Decision notified14 May 2012145 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)