Skip to content
AltUrb
Granted

Rue Royale

Bruxelles · 04/PFU/144172 · Permis d'urbanisme unique délivré par le FD

Rue Royale, Bruxelles: public space. Case octroyé, lodged on 23 July 2002. The decision was notified on 18 July 2003, 360 days after lodging.

aménager une zone 30 dans le quartier Notre-Dame-aux-Neiges.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on23 July 2002date the file was received
Consultation committee17 December 2002
Decision notified18 July 2003360 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Consultation committee
  4. Decision notified · Granted
  5. Declared incomplete

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)