Place De Brouckère 31
Bruxelles · 04/PFU/551916 · Permis d'urbanisme unique délivré par le FD
Place De Brouckère 31, Bruxelles: heavy renovation. Case octroyé, lodged on 31 October 2014. The decision was notified on 9 December 2014, 39 days after lodging.
Restaurer des plafonds moulures classes du hall d’entrée et du jardin d’hiver de l’hôtel Métropole suite au dégât des eaux survenu dans la nuit du 4 juin 2014.| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 31 October 2014 | date the file was received |
| Decision notified | 9 December 2014 | 39 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Façade and windows | REMPLACER DES FENÊTRES À GUILLOTINE ET RESTITUTION DES DOUBLES PORTES DE LA FUTURE RÉCEPTION | 2026 |
| 6 m | Other | Réaliser des études et des sondages préalables | 2023 |
| 16 m | Heavy renovation | Rénover les parties non classées de l’hôtel Métropole, installer un espace spa avec piscine au sous-sol et modifier et a | 2023 |
| 17 m | Heavy renovation | Restaurer les parties classées de l'Hotel Métropole. | 2023 |
| 35 m | Signs and advertising | 7 parallelle uihangborden plaatsen | 2025 |
Other nearby cases : 04/PFU/1970427, 04/PU/1966198, 04/PFD/1967679, 04/PU/1836200, 04/PU/1900007, 04/PU/1975507, 04/PU/1830136, 04/PU/1894332, 04/PU/1905296, 04/PFU/1835969, 04/PU/1837105, 04/PU/1850903, 04/PU/1905973, 04/PFU/1942811, 04/PU/1943143, 04/PFU/1994196, 04/PU/2013356, 04/PU/2030888, 04/PFU/1848711, 04/PU/1929991, 04/PFU/1976145, 04/PU/1859218, 04/PU/1933559, 04/PFU/1906351, 04/PFU/1947677
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)