Harenberg 79
Bruxelles · 04/PU/1797588 · Permis d'urbanisme privé
Harenberg 79, Bruxelles: tree felling. Case octroyé, lodged on 30 August 2021. The decision was notified on 9 December 2021, 101 days after lodging.
abattre 2 arbres (Betula pendula et Prunus serrulata)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 August 2021 | date the file was received |
| Decision notified | 9 December 2021 | 101 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 85 m | New construction | construire un immeuble avec deux duplex | 2023 |
| 85 m | New construction | construire une maison unifamiliale | 2024 |
| 110 m | New construction | construire un immeuble d'habitation (R+2) composé de 3 logements (lot 1) | 2022 |
| 124 m | Façade and windows | Remplacer les châssis en bois brun par des châssis en PVC de ton gris anthracite (mise en conformité) | 2023 |
| 176 m | Public space | Construire deux ascenseurs sur les quais de la gare de Haren-Sud afin de les rendre accessibles aux personnes à mobilité | 2025 |
Other nearby cases : 04/PFD/2019804, 04/PU/1835122, 04/SFD/1869924, 04/PU/2019240, 04/PU/1860595, 04/PU/1956771, 04/PU/1979376, 04/PU/1846971, 04/PU/1862076, 04/PFD/1895129, 04/PFD/1836201, 04/PFD/1849442, 04/PU/1940919, 04/PU/2029339, 04/PU/1931425, 04/PU/1950038, 04/PFD/1841728, 04/PU/1810861, 04/PU/1847225, 04/PU/1862066, 04/PU/1946377, 04/PU/2044664, 04/PU/1866979
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)