Skip to content
Altaica Urban
Granted

Boulevard de la Plaine 2

Ixelles · 09/IPE/2018890 · Permis d'environnement

Boulevard de la Plaine 2, Ixelles: —. Case octroyé, lodged on 29 January 2026. The decision was notified on 9 March 2026, 39 days after lodging.

42474B1
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on29 January 2026date the file was received
Decision notified9 March 202639 days
Works started9 March 2026
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
94 mStudent housinghet renoveren van een gebouw met studentenkots (van 12 tot 8)2022
154 mChange of useRégulariser un changement d'affectation (chambres d'étudiants transformées en boulangerie, brasserie et laboratoire ) av2023
157 mChange of useGebouw P2 was bestemd voor huisvesting van studenten. Vanwege leegstand werd een herbestemming naar leslokalen doorgevoe2026
157 mChange of useRégulariser le changement d'utilisation de chambres d'étudiants en salle de cours au rez-de-chaussée. 2026
166 mTree fellingabattre 13 arbres à haute tige: 12 robiniers faux-acacia (Robinia pseudoacacia) et 1 ailante glanduleux (Ailanthus altis2025

Other nearby cases : 09/GOU_PU/2028764, 09/PU/1979230, 09/PFD/1986475, 09/PFD/1858985, 09/PFD/2014292, 09/PFD/2039635, 09/PFD/1914265, 09/LPFD/1961655

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)