Krekelenberg 89

Watermael-Boitsfort · 17/PU/1869960 · Permis d'urbanisme privé

Krekelenberg 89, Watermael-Boitsfort: energy works. Case octroyé, lodged on 30 January 2023. The decision was notified on 22 March 2023, 51 days after lodging.

installer des panneaux photovoltaïques sur un toit plat
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on30 January 2023date the file was received
Decision notified22 March 202351 days
Works started24 April 2023
Floor areasnot reported by the source
Competent authorityWatermael-Boitsfort

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
46 mTree fellingabattre 2 thuyas2023
53 mRoofisoler la toiture par extérieur2026
64 mEnergy worksinstaller 34 panneaux photovoltaïques2024
64 mEnergy worksInstallations de 30 panneaux photov. pour autoconsommer l'énergie produite.2024
68 mHeavy renovationrénover une maison unifamiliale2022

Other nearby cases : 17/PU/1853232, 17/PU/1863515, 17/PU/1979849, 17/PU/1866809, 17/PU/2039681, 17/PU/1841170, 17/PU/1838625, 17/PU/2034402, 17/PU/2028693, 17/PU/1910797, 17/PU/1930460, 17/PU/2012545, 17/PU/1907434, 17/PU/1968387, 17/GOU_PU/2029607, 17/PU/2004104, 17/PU/1948815, 17/PU/1979155, 17/PU/1859148, 17/PU/1960341, 17/PU/1799599, 17/PU/1899721, 17/PU/2036393, 17/PU/1831017, 17/PU/1913927