Rue Middelbourg 68
Watermael-Boitsfort · 17/PU/1935717 · Permis d'urbanisme privé
Rue Middelbourg 68, Watermael-Boitsfort: energy works. Case octroyé, lodged on 5 March 2024. The decision was notified on 7 June 2024, 94 days after lodging.
installer 34 panneaux photovoltaïques| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 5 March 2024 | date the file was received |
| Decision notified | 7 June 2024 | 94 days |
| Floor areas | — | not reported by the source |
| Competent authority | Watermael-Boitsfort |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Energy works | Installations de 30 panneaux photov. pour autoconsommer l'énergie produite. | 2024 |
| 29 m | Tree felling | abattre 1 arbre | 2022 |
| 46 m | Tree felling | abattre 2 thuyas | 2023 |
| 52 m | Regularisation | régulariser l'aménagement des abords-parkings non conformes au permis d'urbanisme 23.405 délivré par le collège des Bou | 2022 |
| 64 m | Energy works | installer des panneaux photovoltaïques sur un toit plat | 2023 |
Other nearby cases : 17/PU/1910797, 17/PU/2004104, 17/GOU_PU/2029607, 17/PU/1968387, 17/PU/1979155, 17/PU/1907434, 17/PU/2012545, 17/PU/1799599, 17/PU/2036393, 17/PU/1831017, 17/PU/1859148, 17/PU/2026882, 17/PU/2039681, 17/PU/1979849, 17/PU/1841170, 17/PU/1838625, 17/PU/1866809, 17/PU/1858329, 17/PU/2034402, 17/PU/1927192, 17/PU/1870015, 17/PU/2015960, 17/PU/2014474, 17/PU/1981508, 17/PU/2028693
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)