Granted
Place de l'Alma 2
Woluwe-Saint-Lambert · 18/IPEPLP/1900767 · Prolongation de PE
Place de l'Alma 2, Woluwe-Saint-Lambert: operation of installations. Case octroyé, lodged on 2 May 2023. The decision was notified on 3 May 2024, 367 days after lodging.
Exploitation d’un établissement scolaire de l’enseignement supérieur| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 2 May 2023 | date the file was received |
| Decision notified | 3 May 2024 | 367 days |
| Works started | 15 May 2024 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 71 m | Change of use | changer l'affectation d'un local semi-enterré de cave en commerce alimentaire BIO de proximité et mettre en place des en | 2023 |
| 91 m | Split into dwellings | régulariser un appartement d'une chambre au troisième étage et les modifications effectuées sur les terrasses et façades | 2025 |
| 110 m | Tree felling | Demande de permis pour abattre un arbre mort et plantation de nouveaux arbres | 2025 |
| 112 m | Signs and advertising | Placer, déplacer, adapter, régulariser des caméras de surveillance du site Proposer un modèl unique pour l'ensemble du | 2021 |
| 138 m | Façade and windows | Remplacer les menuiseries extérieures et les stores solaires du bâtiment "Galien" sur le site de l'UCLouvain | 2022 |
Other nearby cases : 18/PFD/1909558, 18/PU/1871605, 18/PU/1928088, 18/PU/1821447
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)