Skip to content
Altaica Urban
Granted

Avenue Orban 193

Woluwe-Saint-Pierre · 19/IPEPLP/496379 · Prolongation de PE

Avenue Orban 193, Woluwe-Saint-Pierre: —. Case octroyé, lodged on 13 January 2014. The decision was notified on 26 January 2015, 378 days after lodging.

Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on13 January 2014date the file was received
Decision notified26 January 2015378 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mEnergy worksplacer une cabine à haute-tension, 4 cabines électriques et créer 4 emplacements de parking pour la recharge de voitures2023
18 mHeavy renovationModifier des baies et l'aménagement intérieur (Modification du PU DB005/2020)2022
46 mTree fellingabattre un arbre en zone de recul2023
46 mTree fellingAbattre un arbre2022
46 mTree fellingAbattre un arbre2022

Other nearby cases : 19/PU/2007128, 19/PU/1896704, 19/PU/1822812, 19/PU/1811480, 19/PU/1897098, 19/SFD/1845163, 19/AA/2039875, 19/PU/1962862, 19/AA/1913261, 19/PU/1832486, 19/PU/1915182, 19/PU/2027062, 19/PU/1831644, 19/PU/1979782, 19/PU/1851267, 19/PU/1986666, 19/PU/2013298, 19/PU/2014434, 19/PU/1903744, 19/PU/1931389, 19/PU/1895718, 19/PU/1962620, 19/PFD/1962324, 19/PU/1947646, 19/PU/1851419

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)