Avenue de Tervueren 245

Woluwe-Saint-Pierre · 19/PFD/400979 · Permis d'urbanisme délivré par le FD

Avenue de Tervueren 245, Woluwe-Saint-Pierre: tree felling. Case octroyé, lodged on 9 February 2011. The decision was notified on 8 March 2011, 27 days after lodging.

Abattre deux arbres.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on9 February 2011date the file was received
Decision notified8 March 201127 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
43 mNew constructionRégulariser deux abris de jardin installés au fond du jardin.2024
43 m19/PU/19388612024
43 m19/PU/19341282024
43 mEnergy worksInstaller des panneaux photovoltaïques sur le versant arrière de la toiture et sur la toiture plate à l'arrière et régul2024
48 mRegularisationrégularisation d'un immeuble2023

Other nearby cases : 19/PFU/1948879, 19/PU/1974609, 19/PU/1989473, 19/PU/2035476, 19/PU/1950384, 19/PU/1867780, 19/PU/1937898, 19/PU/1811112, 19/PU/1949649, 19/PU/2025951, 19/PU/1995212, 19/PU/1971144, 19/PU/1832861, 19/PU/1979324, 19/AA/1825647, 19/PU/2012225, 19/PFU/2042563, 19/PU/1943508, 19/PU/2036127, 19/SFD/1834236, 19/PU/1850036, 19/PU/1871441, 19/PFD/1904975, 19/PU/1966487, 19/PU/2014494