Granted
Avenue Houba de Strooper 750 (NAAST)
Bruxelles · CL2/592181 · Permis d'environnement communal Classe 2
Avenue Houba de Strooper 750 (NAAST), Bruxelles: operation of installations. Case octroyé, lodged on 9 February 2016. The decision was notified on 22 June 2016, 134 days after lodging.
parking verbranding ventilatoren| Permit type | Permis d'environnement communal Classe 2 | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 February 2016 | date the file was received |
| Public inquiry | 13 May 2016 – 28 May 2016 | |
| Decision notified | 22 June 2016 | 134 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 31 m | Extension or raising | fermer une terrasse au niveau du sous-sol (niveau jardin) | 2022 |
| 53 m | Demolition and reconstruction | Avenue Houba de Strooper, d'une part, diviser une maison unifamiliale en 3 studios et un rez-de-chaussée commercial, ave | 2021 |
| 77 m | Office conversion | transformer des bureaux en équipement médical de 282m² | 2024 |
| 93 m | Signs and advertising | placer 1 mobilier urbain d’information avec support de publicité (BXL0537MU) | 2021 |
| 97 m | Split into dwellings | aménager un deuxième et un troisième appartement de 2 chambres chacuns au 2e et au 3e étage de l'immeuble comportant déj | 2024 |
Other nearby cases : 04/PU/1857721, 04/PU/1835197, 04/PFD/1978477, 04/PU/1996142, 04/PU/1831946, 04/PU/1858074, 04/SFD/1830921, 04/PFD/1906208, 04/PU/1944121, 04/PU/1967148, 04/PU/2000101, 04/PU/1846141, 04/PU/1871845, 04/PU/1983985, 04/PU/1962043, 04/PU/2029776, 04/SFD/1901610
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)