Granted

Rue du Noyer 282

Schaerbeek · PU/193845 · Permis d'urbanisme privé

Rue du Noyer 282, Schaerbeek: merger of dwellings. Case octroyé, lodged on 7 December 1999. The decision was notified on 3 April 2000, 118 days after lodging.

Réunir 2 logements en un seul +4 et installer bureaux (178 m²)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on7 December 1999date the file was received
Decision notified3 April 2000118 days
Floor areasnot reported by the source
Competent authoritySchaerbeek

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mOtherPlacer une protection réversible contre les pigeons sur les balcons des façades intérieures des blocs 1 et 22023
0 m15/PU/18327312022
0 mSplit into dwellingsRégulariser 2 unités de logement au sein d'une copropriété (au lieu de 1 unité de logement stipulé dans la situation de 2022
0 mFaçade and windowsPlacer un double vitrage dans des menuiseries extérieures classées.2025
31 mFaçade and windowsPlacer un double vitrage dans des menuiseries extérieures classées.2025

Other nearby cases : 15/PFU/2020233, 15/PU/2020707, 04/PU/1821933, 04/PU/1866250, 04/PU/1837277, 15/PFD/1984355, 15/PU/1984466, 15/PFD/1959573, 15/SFD/1826202, 15/PU/1912755, 15/GOU_PU/1966863, 04/PU/1990854, 15/PU/2004810, 15/PU/1938664, 15/PU/2028698, 04/PU/1908600, 15/PU/1959484, 15/PU/1994146, 15/PU/1995283, 04/PU/1913451, 04/PFU/1849086, 15/PU/2006847, 04/PU/2031464, 15/PU/2042277, 15/ENS/2004525