Avenue Charbo 009
Schaerbeek · PU/194877 · Permis d'urbanisme privé
Avenue Charbo 009, Schaerbeek: extension or raising. Case octroyé, lodged on 19 July 2004. The decision was notified on 8 April 2005, 263 days after lodging.
Construire annexe 0, fermer balcons arrières, installer cabinet médical 0| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 July 2004 | date the file was received |
| Public inquiry | 5 November 2004 – 20 November 2004 | |
| Consultation committee | 10 December 2004 | |
| Decision notified | 8 April 2005 | 263 days |
| Floor areas | — | not reported by the source |
| Competent authority | Schaerbeek |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 12 m | Extension or raising | RÉALISÉ - dans un immeuble de 3 logements, étendre le logement du 2ème étage aux combles, mettre en conformité et modifi | 2022 |
| 50 m | Change of use | dans un immeuble à usage mixte comprenant 4 commerces au rez-de-chaussée et 64 logements aux étages, mettre en conformit | 2026 |
| 65 m | Extension or raising | dans un immeuble de 9 logements, mettre en conformité la fermeture d'un balcon au 1er étage (coté gauche) du logement tr | 2026 |
| 65 m | Heavy renovation | dans un immeuble de rapport de neuf logements, régulariser la modification de la répartition des logements par l'aménage | 2026 |
| 80 m | Split into dwellings | CADUQUE_dans un immeuble mixte (1 activité productive et 3 logements), mettre en conformité l’ajout d’un logement (total | 2025 |
Other nearby cases : 15/PU/2041601, 15/PU/1978375, 15/PU/2012070, 15/PFD/1854379, 15/PU/1978374, 15/PU/1912252, 15/PU/1946611, 04/PU/1908281, 15/PU/1845742, 15/PU/2008891, 15/PU/1953812, 04/PU/1981469, 04/PU/2038372, 04/PFU/1954932, 04/PU/1848873, 15/PU/1834955, 04/PU/1937134, 04/PFU/1936933, 04/PU/1954985, 15/PU/1843337, 15/PU/1949009, 04/PU/1829904, 04/PFU/2029639, 04/PFU/2028446, 04/PU/1850500
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)