Skip to content
Altaica Urban
Granted

rue Emile Pathé 408

Forest · PU/268488 · Permis d'urbanisme privé

rue Emile Pathé 408, Forest: new construction. Case octroyé, lodged on 31 October 2002. The decision was notified on 7 August 2003, 280 days after lodging. It comprises 2 dwellings.

bouwen van twee units/semi-industriele gebouwen/magazijn/werkplaats
The application's own description, in its source language (NL). Source: Nova.
2
Dwellings created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on31 October 2002date the file was received
Public inquiry15 February 2003 – 3 March 2003
Consultation committee13 March 2003
Decision notified7 August 2003280 days
Floor areasnot reported by the source
Competent authorityForest

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)