Chaussée de Stockel 377, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 5 March 2012. The decision was notified on 13 March 2012, 8 days after lodging.
Réaménagement des abords d'un commerce et const d'un abri de jardin et d'une terrasse sur pilotis| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 5 March 2012 | date the file was received |
| Decision notified | 13 March 2012 | 8 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | Construction d'un immeuble mixte composé d'un commerce et de 3 unités de logements | 2021 |
| 0 m | Demolition and reconstruction | Démolir un bâtiment et construire un immeuble mixte composé d'un commerce et de 3 unités de logements | 2022 |
| 23 m | Roof | créer deux lucarnes en toiture, isoler la façade arrière et les extensions et transformer une habitation unifamiliale mi | 2026 |
| 26 m | Roof | régulariser, créer une lucarne en façade arrière et isoler le pignon mitoyen et la façade arrière d'une habitation unifa | 2026 |
| 71 m | Heavy renovation | régulariser et transformer un immeuble de rapport | 2025 |