Granted
Harenberg 39
Bruxelles · PU/511803 · Permis d'urbanisme privé
Harenberg 39, Bruxelles: new construction. Case octroyé, lodged on 7 March 2003. The decision was notified on 19 June 2003, 104 days after lodging.
construction d'une maison unifamiliale| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 March 2003 | date the file was received |
| Decision notified | 19 June 2003 | 104 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Decision notified · Granted
- Declared complete
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 132 m | New construction | construire un immeuble avec deux duplex | 2023 |
| 132 m | New construction | construire une maison unifamiliale | 2024 |
| 163 m | Public space | Construire deux ascenseurs sur les quais de la gare de Haren-Sud afin de les rendre accessibles aux personnes à mobilité | 2025 |
| 171 m | New construction | construire un immeuble d'habitation (R+2) composé de 3 logements (lot 1) | 2022 |
| 183 m | Façade and windows | Remplacer les châssis en bois brun par des châssis en PVC de ton gris anthracite (mise en conformité) | 2023 |
Other nearby cases : 04/PU/1866979, 04/PU/1931425, 04/PU/2029339, 04/PU/2044664, 04/PU/1847225, 04/SFD/1869924, 04/PU/1835122, 04/PFD/1841728, 04/PU/1950038, 04/PU/1860595, 04/PFD/1895129, 04/PFD/1849442, 04/PFD/1836201, 04/PFD/2019804, 04/PU/2019240, 04/PU/1862076
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)