Rue du Petit Rempart, Bruxelles: change of use. Case octroyé, lodged on 28 May 2004. The decision was notified on 20 December 2004, 206 days after lodging.
modifier le rez commercial en logement (modification au permis délivré - dossiers 14S/03 et 52S/01)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 May 2004 | date the file was received |
| Consultation committee | 7 September 2004 | |
| Decision notified | 20 December 2004 | 206 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.