Skip to content
AltUrb
Granted

Harenberg 178

Bruxelles · PU/515648 · Permis d'urbanisme privé

Harenberg 178, Bruxelles: new construction. Case octroyé, lodged on 4 July 2005. The decision was notified on 5 May 2006, 305 days after lodging.

Construction d'une maison unifamiliale (voir nouvelle demande : 10H/07)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on4 July 2005date the file was received
Decision notified5 May 2006305 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
10 mNew constructionconstruire un immeuble de trois logements duplex (lots 3 et 4) et un parking en sous‐sol (14 places dont 2 places PMR)2024
69 mExtension or raisingd'une part, changer les châssis en façade par des châssis en PVC blancs et placer une fenêtre de toiture à l'avant d'une2022
69 mExtension or raisingd'une part, changer les châssis en façade d'une maison unifamiliale par des châssis en PVC blanc, construire une extensi2024
71 mExtension or raisingchanger les menuiseries et installer une grille en façade avant, installer des fenêtres en toiture, poser des panneaux p2022
95 mTree fellingabattre 1 arbre2022

Other nearby cases : 04/SFD/1864995, 04/PU/1936058, 04/PU/1955673, 04/PU/1810861, 04/PU/1979376, 04/PU/1956771, 04/PU/1908294, 04/PU/1837239, 04/PU/2019240, 04/PFD/2019804, 04/PU/1847020, 04/PU/1828968, 04/PU/1862076, 04/PU/1895277, 04/PU/1907673, 04/PU/1950018, 04/PU/1856720, 04/PU/2042729, 04/PFU/1992949, 04/PU/2023467, 04/PFU/2020305, 04/PU/1959497, 04/PU/1860595, 04/PU/1933328, 04/PU/1835122

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)