Rue du Pré aux Oies 5–7
Bruxelles · PU/517087 · Permis d'urbanisme privé
Rue du Pré aux Oies 5–7, Bruxelles: new construction. Case octroyé, lodged on 19 March 2008. The decision was notified on 3 July 2008, 106 days after lodging.
placement de pieux| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 March 2008 | date the file was received |
| Decision notified | 3 July 2008 | 106 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 71 m | New construction | construire une maison unifamiliale | 2024 |
| 71 m | New construction | construire un immeuble avec deux duplex | 2023 |
| 74 m | Public space | Construire deux ascenseurs sur les quais de la gare de Haren-Sud afin de les rendre accessibles aux personnes à mobilité | 2025 |
| 82 m | Demolition and reconstruction | démolir une annexe et une véranda pour construire une nouvelle annexe avec lanterneau | 2022 |
| 82 m | Demolition and reconstruction | démolir une annexe et une véranda pour construire une nouvelle annexe avec lanterneau | 2023 |
Other nearby cases : 04/PU/1860595, 04/PFD/1849442, 04/PFD/1895129, 04/PFD/1836201, 04/PU/1950038, 04/PFD/1841728, 04/PU/1847020, 04/PU/1931425, 04/PU/2029339, 04/PU/1862076, 04/PU/1847225, 04/PFD/2015869, 04/PFD/2019804, 04/PU/2019240, 04/PU/1846971, 04/PU/2044664, 04/PU/1810861, 04/PU/1895277, 04/PU/1939169, 04/PU/1866979, 04/PU/1856720, 04/PU/1940919
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)