Granted
Rue du Petit Rempart 11
Bruxelles · PU/517400 · Permis d'urbanisme privé
Rue du Petit Rempart 11, Bruxelles: split into dwellings. Case octroyé, lodged on 18 December 2007. The decision was notified on 18 March 2009, 456 days after lodging. It comprises 3 dwellings.
Transformer l'immeuble en 3 logements (modifications au permis 11P/06 - travaux déjà réalisés)3
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 December 2007 | date the file was received |
| Public inquiry | 26 September 2008 – 11 October 2008 | |
| Consultation committee | 21 October 2008 | |
| Decision notified | 18 March 2009 | 456 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)