Granted
Rue du Marché au Charbon
Bruxelles · PU/520943 · Permis d'urbanisme privé
Rue du Marché au Charbon, Bruxelles: retail or horeca fit-out. Case octroyé, lodged on 27 February 2009. The decision was notified on 30 September 2010, 580 days after lodging.
Régularisation : aménagement d'une zone de consommation accessoire au commerce et déplacement du conduit d'extraction de la hotte en façade arrière| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 27 February 2009 | date the file was received |
| Decision notified | 30 September 2010 | 580 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)