Granted
Boulevard Simon Bolivar 30
Bruxelles · PU/522656 · Permis d'urbanisme privé
Boulevard Simon Bolivar 30, Bruxelles: heavy renovation. Case octroyé, lodged on 2 December 2011. The decision was notified on 11 July 2012, 222 days after lodging.
Nieuwe ingangen; nieuwe koelgroep op het dak; nieuwe patio's; nieuwe binnentrappen en kleine gevelaanpassingen| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 2 December 2011 | date the file was received |
| Decision notified | 11 July 2012 | 222 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Façade and windows | Modifier les châssis de l'entrée principale de la tour WTC III | 2022 |
| 62 m | New construction | renouveler, pour une durée maximale de 4 ans, l’installation de 13 conteneurs préfabriqués, d’une terrasse et d’une zone | 2023 |
| 62 m | New construction | Demande initiale : Construire sur une partie du site formé par l'actuel immeuble WTC III, après démolition partielle du | 2022 |
| 87 m | Other | Installer une œuvre d'art (Permis Modificatif du 04/PFD/688807). | 2024 |
| 96 m | Signs and advertising | Régulariser vingt-deux dispositifs publicitaires digitaux de 2 m² isolés (MU: 31, 756, 162, 648, 47, 737, 742, 321, 514 | 2026 |
Other nearby cases : 04/PFD/2019649, 04/PFD/1822391, 15/PFD/1961647, 15/PFD/1848776, 04/PFD/1998434, 14/PFD/2037648, 14/PU/1850180, 04/PU/2035010, 04/PU/1984856, 15/PU/1934845, 15/PU/1848298, 04/PU/1832245, 15/PU/1821345, 04/PFD/2020155
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)