Boulevard Simon Bolivar 30

Bruxelles · PU/522656 · Permis d'urbanisme privé

Boulevard Simon Bolivar 30, Bruxelles: heavy renovation. Case octroyé, lodged on 2 December 2011. The decision was notified on 11 July 2012, 222 days after lodging.

Nieuwe ingangen; nieuwe koelgroep op het dak; nieuwe patio's; nieuwe binnentrappen en kleine gevelaanpassingen
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on2 December 2011date the file was received
Decision notified11 July 2012222 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mFaçade and windowsModifier les châssis de l'entrée principale de la tour WTC III2022
62 mNew constructionrenouveler, pour une durée maximale de 4 ans, l’installation de 13 conteneurs préfabriqués, d’une terrasse et d’une zone2023
62 mNew constructionDemande initiale : Construire sur une partie du site formé par l'actuel immeuble WTC III, après démolition partielle du 2022
87 mOtherInstaller une œuvre d'art (Permis Modificatif du 04/PFD/688807).2024
96 mSigns and advertisingRégulariser vingt-deux dispositifs publicitaires digitaux de 2 m² isolés (MU: 31, 756, 162, 648, 47, 737, 742, 321, 5142026

Other nearby cases : 04/PFD/2019649, 04/PFD/1822391, 15/PFD/1961647, 15/PFD/1848776, 04/PFD/1998434, 14/PFD/2037648, 14/PU/1850180, 04/PU/2035010, 04/PU/1984856, 15/PU/1934845, 15/PU/1848298, 04/PU/1832245, 15/PU/1821345, 04/PFD/2020155

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)