Rue du Pré aux Oies lot 3
Bruxelles · PU/527383 · Permis d'urbanisme privé
Rue du Pré aux Oies lot 3, Bruxelles: new construction. Case octroyé, lodged on 16 May 2014. The decision was notified on 29 August 2014, 105 days after lodging. The project creates 254 m² of housing.
construire une maison unifamiliale (PL 2430 lot 3)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 May 2014 | date the file was received |
| Decision notified | 29 August 2014 | 105 days |
| Works started | 1 March 2015 | |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 31 m | New construction | Implanter une cabine à haute tension avec une clôture de sécurité intégrant des haies | 2026 |
| 31 m | New construction | Implantation d'une cabine à haute tension | 2026 |
| 32 m | Extension or raising | placer une véranda rétractable sur la terrasse du 3ème étage | 2022 |
| 72 m | New construction | construire un immeuble d'habitation (R+2) composé de 3 logements (lot 1) | 2022 |
| 73 m | Extension or raising | changer les menuiseries et installer une grille en façade avant, installer des fenêtres en toiture, poser des panneaux p | 2022 |
Other nearby cases : 04/PU/1810861, 04/PU/1907673, 04/PU/1950018, 04/PU/1860595, 04/SFD/1869924, 04/PU/1835122, 04/PFD/1849442, 04/PFD/1895129, 04/PFD/1836201, 04/PU/1856720, 04/PU/1955673, 04/PU/1936058, 04/PU/1940919, 04/PU/2023467, 04/PFD/2015869, 04/PFD/1993577, 04/PU/1895277, 04/PU/1946377, 04/PU/1862066, 04/PU/1956771, 04/PU/1979376, 04/PU/1950038, 04/PU/1837239, 04/PU/1908294, 04/PU/1939169
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)