Avenue Van Crombrugghe 123
Woluwe-Saint-Pierre · PU/632535 · Permis d'urbanisme privé
Avenue Van Crombrugghe 123, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 4 April 2017. The decision was notified on 13 June 2017, 70 days after lodging. The project creates 23 m² of housing.
extension et transformation en toiture de l'habitation unifamiliale mitoyenne| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 April 2017 | date the file was received |
| Public inquiry | 24 April 2017 – 9 May 2017 | |
| Consultation committee | 18 May 2017 | |
| Decision notified | 13 June 2017 | 70 days |
| Works started | 3 April 2018 | |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 26 m | Roof | aménager les combles et régulariser l'habitation unifamiliale mitoyenne | 2022 |
| 32 m | Extension or raising | Transformer et étendre la maison unifamiliale | 2022 |
| 43 m | Extension or raising | étendre, isoler et transformer une habitation unifamiliale mitoyenne | 2026 |
| 46 m | Extension or raising | régulariser et étendre une maison unifamiliale | 2023 |
| 46 m | — | 19/PU/1897071 | 2023 |
Other nearby cases : 19/PU/1913410, 19/PU/2038571, 19/PU/1914114, 19/PFD/1834370, 19/PU/1957254, 19/PFD/2011440, 19/PFD/2025449, 19/PFD/1995894, 19/PU/1860533, 19/PU/1826637, 19/PU/1926708, 19/PU/1868296, 19/PU/1868023, 19/PU/1917253, 19/PU/1995025, 19/PU/1849794, 19/PU/2026697, 19/AA/1843928, 19/PU/1831841, 19/PU/1993355, 19/PU/1846301, 19/PU/1830821, 19/SFD/1838360, 19/PU/1967497, 19/PU/1850946
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)